Wednesday, July 25, 2007

The plumber has started doing his thing, crack and all.


In this picture, you will see the "island" for the kitchen with the plumbing sticking up for the kitchen sink.


Side view of the hardiplank. I think they are mostly done. They are just waiting on one window to be installed in the master bath, then they will finish the siding.


Front view with shake done.


I'm expecting the electricians to be on site TODAY and should have some more pictures soon.

78 days...

Tuesday, July 17, 2007

The hardiplank is making its way around...

Sent via cell phone (mobile blog)

Monday, July 16, 2007

Here are the latest pictures from the last week or so..

On 7/13, they have the roof on (roof, roof roof!) and the Tyvek house wrap on! Lookin' good!





Just a few days later, the windows and doors went in. Here is a shot from the kitchen looking towards the back porch.



Today, 7/16, the siding (hardiplank) gets started.

As of 7/16, view of the front of the house.

Tuesday, July 10, 2007

Email alerts might be working! I have been in touch with feedblitz support and they are trying to troubleshoot the issue.

Stay tuned...

Update!! As of 7/10 it appears email updates are being sent out. I hope you are getting yours! If not, please let me know!

Monday, July 09, 2007

Happy 4th of July!
I felt it would be a good time to raise a flag at the job site. I didn't want to mount the flag on the house (to be in the way of building) so I mounted it on the temp power feed (probably not a good place either). I plan to move the flag over to the inspectors pole in the next day or so..

Here you can see the shell of the house.. Most of the framing is done... They still need to build/install stairs. Once this happens, I will get more pictures of the inside.


I would expect windows to be installed soon as well as the roof shingles.

Here is a cross section of the family room. Looks like they got the fireplace installed.

View from back yard.

Back yard, reverse angle.